Automation rule - original estimate

l.kubon September 28, 2020

Hi, I want to create an automation rule.

If someone changes the value of the original estimate and it won't be in Analysis & Design status or estimate ready then I'll get an email notification about it.

How do I do this? Is it possible?

2 answers

1 accepted

0 votes
Answer accepted
l.kubon September 30, 2020

Ok nevermind i found everything. this is how it looks and works in my project 

original estimation = time tracking 

Zrzut ekranu 2020-09-30 o 11.11.38.png

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 29, 2020

Hi @l.kubon ,

Here is some information to get you started with Automation For Jira:

There are two types of automation:

  • Global: In the Free version, you get 100 executions per product, per month
  • Project: In all versions, you get unlimited executions per month

Automation Basics: https://www.atlassian.com/software/jira/guides/expand-jira/automation

You can do this via global rules to apply to all projects also. You'll need to be a Jira Admin/Site Admin, go to Jira Settings > System > Automation Rules (left-hand menu).

For more on using Automation For Jira see these help pages.

Once you have a rule set up and need additional help, just make a new post here. 

l.kubon September 29, 2020

I know how it works. I have a little problem because I cannot find an original estimate field. 

Why? Zrzut ekranu 2020-09-30 o 08.09.53.png

Eran Kaufman November 25, 2020

haven't managed to find the original estimate as well

any solution for that???

l.kubon November 25, 2020

Original estimate = time tracking 

Zrzut ekranu 2020-11-25 o 11.50.28.png

Eran Kaufman November 25, 2020

thanks! 

I'm now trying to automatically modify the original estimate value, so it'll be the same as the remaining time, but failed to do so... have you managed to do that?

l.kubon November 25, 2020

I wasn't doing something like that. I just set a validator that without giving value original estimate, you cannot go to in progress. 