  • when we create a sub-task, I want to set the Fix Version and the Epic Link from the parent task, and if they are changed in the Task, I want that to change the subtask

when we create a sub-task, I want to set the Fix Version and the Epic Link from the parent task, and if they are changed in the Task, I want that to change the subtask

Ramaiah Pendli January 16, 2017

Hi,

when we create a sub-task, I want to set the Fix Version and the Epic Link from the parent task, and if they are changed in the Task, I want that to change the sub-task as well


1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 16, 2017

You'll need some code for updating the fix version on to the sub-tasks - a listener would be best as it can detect any change and cascade the result.

Epic Link is not a field that will work on sub-tasks.  You'll need to copy it to another field.