currently, when we put hours in the esitmations, GH automatically converts it to days.
It is configured to 8 hours.
so if I set 6h, I would see 0.75d.
How can I set the fields: estimated, remaining, logged not to be converted to days, but be kepts to hours?
Hello.
Did you try 'Administration' > 'System' > 'Issue Features' > 'Time Tracking'?
According to JIRA documentation "To edit JIRA's Time Tracking settings, it must first be disabled. Once you have changed the settings, you will then need to re-enable Time Tracking so that users can log work on issues."
Cheers, Tihomir.