view hours instead of days in estimation field

currently, when we put hours in the esitmations, GH automatically converts it to days.

It is configured to 8 hours.

so if I set 6h, I would see 0.75d.

How can I set the fields: estimated, remaining, logged not to be converted to days, but be kepts to hours?

1 answer

Hello.

Did you try 'Administration' > 'System' > 'Issue Features' > 'Time Tracking'?

According to JIRA documentation "To edit JIRA's Time Tracking settings, it must first be disabled. Once you have changed the settings, you will then need to re-enable Time Tracking so that users can log work on issues."

Cheers, Tihomir.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

211 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you