Sub-tasks are enabled. Looking at an issue in JIRA, I can create a subtask from the "More Actions" menu. But when I look at the same issue on the Greenhopper planning board, I don't see the "Add subtask" option in the issue's action menu.

On a different project in the same JIRA deployment, it is working fine. I've compared the two project's configurations and I can't tell why one is letting me do this and the other isn't. Any ideas on what setting might affect this?

1 answer

1 accepted

1 vote
Accepted answer
Yew Teck En Atlassian Team Aug 14, 2012

Could be the Card Creation option being unchecked: https://confluence.atlassian.com/display/GHKB/Unable+to+Create+Card

This was the problem. Thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,061 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you