unable to add subtask from greenhopper view even though it works elsewhere.

Barry Steinglass May 24, 2012

Sub-tasks are enabled. Looking at an issue in JIRA, I can create a subtask from the "More Actions" menu. But when I look at the same issue on the Greenhopper planning board, I don't see the "Add subtask" option in the issue's action menu.

On a different project in the same JIRA deployment, it is working fine. I've compared the two project's configurations and I can't tell why one is letting me do this and the other isn't. Any ideas on what setting might affect this?

1 answer

1 accepted

1 vote
Answer accepted
Teck-En
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 14, 2012

Could be the Card Creation option being unchecked: https://confluence.atlassian.com/display/GHKB/Unable+to+Create+Card

Barry Steinglass August 17, 2012

This was the problem. Thanks!