unable to add subtask from greenhopper view even though it works elsewhere.

Sub-tasks are enabled. Looking at an issue in JIRA, I can create a subtask from the "More Actions" menu. But when I look at the same issue on the Greenhopper planning board, I don't see the "Add subtask" option in the issue's action menu.

On a different project in the same JIRA deployment, it is working fine. I've compared the two project's configurations and I can't tell why one is letting me do this and the other isn't. Any ideas on what setting might affect this?

1 answer

1 accepted

This widget could not be displayed.
Yew Teck En Atlassian Team Aug 14, 2012

Could be the Card Creation option being unchecked: https://confluence.atlassian.com/display/GHKB/Unable+to+Create+Card

This was the problem. Thanks!

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted 10 hours ago in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

32 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you