sub task created error

Soft Admin March 25, 2014

After I upgrade to JIRA 6.2,I got a error when I created a sub task at one of project, but created on the other project is fine. I also upload the error message here.(jira_error.txt)

Thanks

ERNIE

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 25, 2014

The Gantt chart plugin is causing a problem according to that stack trace. Try removing it and re-testing to confirm it and get back to us.

Soft Admin March 26, 2014

Dear Nic

After I uninstall the Gantt chart plugin,the sub-task is success to be created.How can I do next step,because we buy the licence to use Gantt chart plugin.


Thanks for reply
ERNIE

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 26, 2014

I think you need support from the vendor to work out what is breaking, potentially it's a bug in the product.

Suggest an answer

Log in or Sign up to answer