sprints into version

Hi,

Is it possible to assign a sprint (and multiple sprints) into a version ?

Thanks

2 answers

2 accepted

1 vote
Accepted answer
Thomas Schlegel Community Champion Dec 05, 2017

Hi,

no. Sprints and versions are totally independent items which can't be assigned to each other.

1 vote
Accepted answer

No, there's no direct relationship.

But there's nothing to stop you holding your developers to a 1:1 rule, and the system does tend nudge people toward "sprint X delivers version Y"

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,972 views 19 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you