sprints into version

Jira Median December 5, 2017

Hi,

Is it possible to assign a sprint (and multiple sprints) into a version ?

Thanks

2 answers

2 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 5, 2017

No, there's no direct relationship.

But there's nothing to stop you holding your developers to a 1:1 rule, and the system does tend nudge people toward "sprint X delivers version Y"

1 vote
Answer accepted
Thomas Schlegel
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 5, 2017

Hi,

no. Sprints and versions are totally independent items which can't be assigned to each other.

Suggest an answer

Log in or Sign up to answer