Are you referring to the status of the Story by referring to the pkey itself? If yes, you can check on the issuestatus column present in the jiraissue table. Not sure whether you are referring to this one or not.
Warm regards,
Danial
I am referring to the status - but I want the status at the time the sprint ended....if you look at the velocity chart, I'm basically trying to figure out how they determine commitment versus completed story points for a sprint. I've got to believe that this information is stored somewhere in the db and it cannot be status as the status potentially changes after an iteration is complete.