show subtask hours in view issue screen

Yen Pham December 8, 2016

From within the view issue screen (i.e. https://liveops.atlassian.net/browse/xxx-yyy) can you make the sub tasks show the remaining estimates in numbers without hovering over the graphical bar?

1 answer

1 vote
Karalee Kikiros
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 8, 2016

Hi Yen. You can edit the jira.table.cols.subtasks in your JIRA Admin > System | General Setings > Advanced Settings to show Remaining Estimate as well or instead of Progress. If you have not done this before though, I strongly suggest that you change it in your sandbox instance before playing around with it in your actual instance

Yen Pham December 9, 2016

Hi Karalee - thanks for that; do you know what the value name is for remaining estimate?

Karalee Kikiros
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 13, 2016

It should be remainingEstimate

Stefan Zerjatke September 22, 2017

The value "timeestimate" worked for me.

For orginal estimate use "timeoriginalestimate".