In the Agile Gadget burndown chart, non-work days are omitted, however, when viewing the rapid board in report mode showing the burndown chart, non-work days are included. Is there a way to have the rapid board exclude non-work days, or a plan to implement this in the future?

2 answers

1 accepted

1 vote
Answer accepted
Dobroslawa Wierzbicka
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 16, 2013

To all still interested, the situation has changed as of Greenhopper 6.1.1: it's now possible to highligt non-working days in the chart, and exclude them from the burndown guideline.

John Burns
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 16, 2013

The new functionality is awesome! Thanks!

1 vote
sclowes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 18, 2012

Hi John,

There are no plans to implement the current 'non working days' configuration from the Planning/Chart/Task and Released boards because they are inadequate for distributed teams or handling public holidays etc.

We would like to look at this in the future but there are no immediate plans.