number of hours per day

If we change the number of hours per day (eg 8 to 6), how does this influence the % FTE in Folio?

wkr,
Wim

1 answer

1 accepted

0 votes
Accepted answer

HI Wim,

Not sure that I fully understand your question...

All folios have their own Hours per day setting.
When you create a folio the default value is based on the "Hours per day" set in JIRA.
So if you change it in JIRA then your existing folios wont be affected.
If you change the ones in your folios then all positions will be recalibrated to the new hours per day value.

Hope this helps.

Cheers
JC

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,446 views 15 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you