moving issues

I moved all the issues from Project A to Project B. All of the standard issues moved fine but the sub tasks did not move. Now I have issues in Project B and their sub tasks in project B. How do I make the sub-tasks to move to project A? It is become really difficult to track issues and sub tasks, even though linked, they are in two different projects.

1 answer

0 votes
Jason Worley Atlassian Team Feb 23, 2015

The bulk move operation can be performed on both standard issues and sub-task issues but you need to move the sub-task to a new issue type based on issue's parent project that it moved too.

More details on that here:
https://confluence.atlassian.com/display/Cloud/Modifying+Multiple+('Bulk')+Issues#ModifyingMultiple('Bulk')Issues-bulkmove

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 29, 2018 in Jira

How to set up an incident workflow from the VP of Engineering at Sentry

Hey Atlassian community, I help lead engineering at Sentry, an open-source error-tracking and monitoring tool that integrates with Jira. We started using Jira Software Cloud internally last year, a...

1,087 views 0 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you