moving issues

I moved all the issues from Project A to Project B. All of the standard issues moved fine but the sub tasks did not move. Now I have issues in Project B and their sub tasks in project B. How do I make the sub-tasks to move to project A? It is become really difficult to track issues and sub tasks, even though linked, they are in two different projects.

1 answer

This widget could not be displayed.
Jason Worley Atlassian Team Feb 23, 2015

The bulk move operation can be performed on both standard issues and sub-task issues but you need to move the sub-task to a new issue type based on issue's parent project that it moved too.

More details on that here:
https://confluence.atlassian.com/display/Cloud/Modifying+Multiple+('Bulk')+Issues#ModifyingMultiple('Bulk')Issues-bulkmove

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

130 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you