i am using the live plan in portfolio 2.0 and it works great so far. I have also configured the hierarchy and created new level for "Initiative", tied to a new issuetype called "Initiative". I am now able to see initiatives in my scope view.
Now, in the scope view, I can create initiatives, create epics under the initiative and stories under the epics. But I have alot of Epics in JIRA Projects that I want to be able to bring under new initiatives that I create.
In classic plans i used to be able to select a epic and select "Move to Initiative", portfolio 2.0 doesn't seem to have this option or may be I am missing something.
Any help is greatly appreciated.
I think all you need to do is add the Initiatives field to the scope view and then select the appropriate intiative.
It took a bit of searching, but I was able to assign existing epics into an initiative. The Initiatives field is not available when the scope view is set to Initiative. I had to change the scope view to show epics, and then I was able to make the Initiatives field visible and assign a parent initiative.
I haven't tried it out, but I'm assuming you can only assign the level relationship when viewing the level below.
ie:
Level 1 - Initiative
Level 2 - Epic
Level 3 - Story
Level 4 - SubTask.
You can only assign an Epic to an Initiative when viewing Epics, and you can only assign stories to an Epic when viewing stories.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to administer the hierarchy setting in Admin - addOns first. Add a level and assign your initiative issue type.
After that you can select the level and use it like the default levels Epic - Story - Subtask.