in jira portfolio what is a resource limit violation?

What is a resource limit violation error in JIRA Portfolio?

1 answer

Not sure if this is an issue in Portfolio 2.0, but I have the fix for the legacy version

Drove me crazy all day and just figured it out.

 

Under: Plan > Configure > Planning > Scheduling

Scroll all the way down to: "Maximum resources"

Increase the number of resources to the maximum you want to have collaborating on them at the same time.

 

Good luck!

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,104 views 13 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot