in jira portfolio what is a resource limit violation?

What is a resource limit violation error in JIRA Portfolio?

1 answer

Not sure if this is an issue in Portfolio 2.0, but I have the fix for the legacy version

Drove me crazy all day and just figured it out.

 

Under: Plan > Configure > Planning > Scheduling

Scroll all the way down to: "Maximum resources"

Increase the number of resources to the maximum you want to have collaborating on them at the same time.

 

Good luck!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,637 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you