Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,466,100
Community Members
 
Community Events
176
Community Groups

i want to calculate estimate And Time Spent in Progress Diffrence And Then Get result in new field

I want to Calculate Orignal Estimate And Time Spent in "in Progress" Status and Then Populate Diffrence in new Field 
OE-Time spent=Field Value(In Min Or Hours)

Example estimate is 3h but spent time is 2h30m Then My New Field Show 30m 

 

1 answer

1 accepted

0 votes
Answer accepted

Hey @Shahbaz Sharif please take a look at this discussion - don't you see the remaining time as it was explained there? :) https://community.atlassian.com/t5/Jira-questions/Remaining-Time-calculations/qaq-p/970670

Please comment if that helps, if not - we will look more into this.

Actually i think log work method is useless in our environment because if someone is late from estimate he may not log time correctly 

I use a free tool called time in status free it calculate time spent in "in progress"  state and give me the result so i want to do following calculations 

Original estimate - time spent in "in progress" = actual time lefy from estimate (+ve or - ve) 

Okay, so what is below is just my thoughts I wanted to share, I hope that's okay with you :)


The problem here might be that not all time the issue spends in progress should actually be considered "I worked on that issue" time.

You would have to consider that if the estimate was 16 hours, it does not mean it will be done in two days - nobody really works on issues 8 hours a day, they make coffee and go to bathroom and go to meetings etc.  Sometimes two issues are in progress because dev started looking at another issue while the first was being deployed etc. relying on the "time spend in progress" will require a lot of discipline form the people on the issues - to move it out of the column if they are not actively working on it, if they go on meetings etc.

"og work method is useless in our environment because if someone is late from estimate he may not log time correctly " - this, just IMO, may indicate that the problem you are trying to solve is not of a technical nature, but rather that the inability to use the default measurement comes from some underlying problems of why the time-log data are unreliable and how it could be fixed. 


Bloompeak Support Marketplace Partner Dec 07, 2022

Hi @Shahbaz Sharif ,

Using Status Time Free tool you get in progress status duration and original estimate columns and export the report into Excel. Then you can calculate the time difference between two in Excel.

Thanks !! Works Fine For Me.

Suggest an answer

Log in or Sign up to answer