i dont see original estimate in JIRA software

Jai CR June 21, 2016

Am not able to see the Original estimate field. Am able to log my work but the original estimate How to I enter? Am using JIRA software

1 answer

1 accepted

0 votes
Answer accepted
Steven F Behnke
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 21, 2016

Have you added the Time Tracking field to your screen?

Jai CR June 22, 2016

Time tracking is enable and am seeing it. Am able to log work. But once I log in some hours, the Estimated and Remaining shows up as 0. Because I don't see an option to enter the Original estimate. Am using trail version but still it should be working I suppose.