i dont see original estimate in JIRA software

Am not able to see the Original estimate field. Am able to log my work but the original estimate How to I enter? Am using JIRA software

1 answer

1 accepted

0 votes
Accepted answer
Steven Behnke Community Champion Jun 21, 2016

Have you added the Time Tracking field to your screen?

Time tracking is enable and am seeing it. Am able to log work. But once I log in some hours, the Estimated and Remaining shows up as 0. Because I don't see an option to enter the Original estimate. Am using trail version but still it should be working I suppose.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,729 views 17 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you