how to set issue dates acording to milestones?

Naz September 19, 2012

Is there a way that Jira can set due dates for issues atomatically based on the milestone dates that they are tied to?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 19, 2012

No. Mostly.

I'm assuming by "milestone" you mean a Jira version. Two problems - first, an issue can be tagged with more than one version, so you'd need to think about how you handle that. Second is that you're going to need to find or write a bit of code to implement this facility. I can't see it being horrendously hard, but you've said you're using OnDemand, so you won't be able to install whatever you write or find.