how to re-write/change the created date of an task/issue?

Abhinav Veeramalla February 25, 2016

how to re-write/change the created date of an task/issue?

1 answer

1 vote
Joe Pitt
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 25, 2016

You can't. If you are importing from another system and want to maintain the create date from that system you should create a new field like 'Original Create Date' and populate it with the value from the other system when you import the data. Only put the field on the 'View' screen so no one can edit it.