how story points give to task

i have  an Module like user access management creation via developer. it take 60 hours to complete how can i added story points for this

1 answer

0 vote

I'm sorry, but this does not make a lot of sense.

I think you are asking how to show an estimate of 60 hours in story points.  There are two broad answers I might give based on a guess at what you are asking:

  1.  Put the story point field on the issues you are raising to cover this work
  2. That is not what story points are for, and you should be using "original estimate" instead. 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

Meet the AUG leaders of Northern Virginia

@Rachel Wright (Jira Genie), @Billy Poggi (AUG NOVA, DC), and @Dana Jansen (Confluence Queen) are just some of the folks that lead one of the world's most active Atlassian User Group (AUG)....

134 views 5 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you