how story points give to task

i have  an Module like user access management creation via developer. it take 60 hours to complete how can i added story points for this

1 answer

0 vote

I'm sorry, but this does not make a lot of sense.

I think you are asking how to show an estimate of 60 hours in story points.  There are two broad answers I might give based on a guess at what you are asking:

  1.  Put the story point field on the issues you are raising to cover this work
  2. That is not what story points are for, and you should be using "original estimate" instead. 

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,316 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot