epics with epic status Done still show on agile board

Louise Simonds June 24, 2016

I have configured the context correctly for the Epic Status custom field, but the Mark As Done link still does not appear in the down-arrow menu for the Epic on the Agile Board.  I have only 1 context configured, the 3 recommended values are configured, and I added all the relevant projects to the context then did a re-index just to be sure.

In an attempt to work around this issue, I added the Epic Status field to the edit screen and manually marked it as Done.  The Epic still appears on the Agile Board even though it is in Done state.  

What am I missing?

1 answer

0 votes
Donell Peters June 24, 2016

You can modify the Board filter and remove issues with Done status, then remove that column from the Board.