ending a sprint

I want to complete a sprint but when I clicked complete sprint it says my incomplete issues will be placed at the top of the back log, I want them to carry over to the next sprint. Can someone help me?

2 answers

This widget could not be displayed.

If the new sprint has been created before you close the old one, it should move them into the new one automatically.

This widget could not be displayed.

Nic is right.

 

A good practice is to have the next sprint already open (usually we have the next 2 sprint)

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

264 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you