Hi, I am new on Jira.
How I create a sub task that is dependant on another one? This task could be a subtask but must be executed when the main task is done. How do I manage that?
So, in this case if I have task 1 and task 2 which I need to do task 2 only when task 1 is done, so I would create task 2 and subtask 1 with the rule that task 2 can not be closed until task 1 is done, is that right?
Not quite. You'd have Task 1.
Task 2 would be a sub-task of 1. You would not be able to close 1 until 2 has reached a certain state.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Edit the workflow for Task 1, and look at the "conditions" on the transition into "done". You will want to add the "sub task blocking" condition to it (you don't need to worry about the sub-task workflow having this condition, or if there are no sub-tasks on a parent - if there are no sub-tasks, it won't block anything)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The usual thing to do is have a workflow for the main issue that includes a condition "can not close this issue when it has open sub-tasks". That condition is a standard one available in JIRA off-the-shelf. A second option is in JIRA Software - a main issue can be moved to done when its last sub-task is closed.
With a little bit of code (provided by add-ons), there are variants - automatically transitioning sub-tasks when a main issue changes, or changing issues based on issue links rather than sub-tasks.