Is it possible, to set this behaviour:

You will be able to close an issue only when all subtask will be closed ... this is really important for me. Issue represents a Test Case, subtask is a Bug from the Test Case. You should close the Test Case only when all subtasks (bugs) are closed...

thank you

1 answer

1 accepted

3 votes

Use the subtask blocking condition in JIRA workflow.

thank you for advice

but please can you help me, how to set a condition in workflow? i am googling right now, but if you know it, you can save my time :) i have jira about 2 days ... thank you

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,313 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot