changing original estimate is not adjusting the remaining estimate value

 

1 answer

1 vote

Indeed. This is intended behaviour, as you should not change your original estimate anymore once you started work on an issue. Changing your original estimate automatically makes it not your original estimate anymore, but an updated estimate.

So once you started, only update your remaining estimate. If you spend more time than originally estimated, so be it. That's part of the learning process of estimations. But track remaining time using your remaining estimates, not by manipulating your original estimates.

On a side note ... as long as you haven't started work, just clear the value of your remaining estimate while editing the issue. JIRA will then align Original and remaining estimates as you save.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

300 views 3 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you