changing original estimate is not adjusting the remaining estimate value

 

1 answer

This widget could not be displayed.

Indeed. This is intended behaviour, as you should not change your original estimate anymore once you started work on an issue. Changing your original estimate automatically makes it not your original estimate anymore, but an updated estimate.

So once you started, only update your remaining estimate. If you spend more time than originally estimated, so be it. That's part of the learning process of estimations. But track remaining time using your remaining estimates, not by manipulating your original estimates.

On a side note ... as long as you haven't started work, just clear the value of your remaining estimate while editing the issue. JIRA will then align Original and remaining estimates as you save.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

259 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you