change "Working hours per day" by a decimal value

Fabien Havard May 3, 2017

Dear all,

on Jira cloud application, in the "time tracking configuration" screen, I am trying to change the "working hours per day" from 8 to 8.5 hours.

I can save the new value, which is updated on the time tracking configuration screen.

But the new value is not really taken into account by Jira and when I refresh the time tracking configuration screen, the value by default (8 hours) is back.

do you have a solution ?

Thanks a lot

1 answer

1 accepted

0 votes
Answer accepted
Fabien Havard May 3, 2017

after investigation, the number of hours shown in the configuration screen is wrong. The new value has been taken into account

Suggest an answer

Log in or Sign up to answer