can you have dependencies between stories belonging to different portfolio plans.

Gabi Samra March 11, 2015
 

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 12, 2015

Not inside portfolio. You can create dependency issue links (between any 2 JIRA issues) but that won't affect the portfolio plan and its scheduling.