Our team has tasks driven from two different sources that are managed by two different projects.
We need to estimate and log work against known tasks at the start of a sprint, as well as for additional tasks during a sprint.
But I want to plan and manage the sprint in one Agile board that includes tasks from both projects.
Is this possible? If so, how?
Yes. That's the simple answer.
All you need to do is change the filter for the Agile board so that it includes both projects. Then you'll see all the issues together and can drag them into the sprint as required.