can an agile sprint include tasks from multiple projects?

Hey there,

Our team has tasks driven from two different sources that are managed by two different projects.

We need to estimate and log work against known tasks at the start of a sprint, as well as for additional tasks during a sprint.   

But I want to plan and manage the sprint in one Agile board that includes tasks from both projects.

Is this possible?  If so, how?

1 answer

1 accepted

0 votes

Yes.  That's the simple answer.

All you need to do is change the filter for the Agile board so that it includes both projects.  Then you'll see all the issues together and can drag them into the sprint as required.

Oh perfect! Thanks mate.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,129 views 13 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot