When I display the Burndown chart, I have only charts for open and done tickets. Or I wan to display other tickets's status lthat I have in my Sprint board. How to add them in the chart configuration?
Thank you,
Oumayma
No. Burndown is defined by "is this done?". If it is done, you burn down. If it is not, you do not.
Other states do not matter to this. It would not be a burndown chart if it did (more like a control chart or cumulative flow)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No. Burndown is defined by "is this done?". If it is done, you burn down. If it is not, you do not.
Other states do not matter to this. It would not be a burndown chart if it did (more like a control chart)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No the burndown focuses on undone vs. done only. every status that is NOT in the right-hand most column of your board is considered undone
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
so where I can a chart that displays all tickets status for me except Cumulative Flow Diagram? (I need a one with story points and not with number of tickets)
Thank you!