burn down charts

Hello ,

I have added a gadget showing burndown chart . It displays Story Points on the y axis where as I want to see No of estimated and work hours Vs Date . How can I do that

2 answers

1 accepted

0 votes
Accepted answer

You need to configure the agile board: Go to the Agile view, Board (upper-right corner) -> Configure. Then set Estimation to Original Time Estimate. This will however affect all users, it does not only concern your gadget. I do not think there is a way to set this only in the gadget.

https://confluence.atlassian.com/display/AGILE063/Configuring+Estimation+and+Tracking

Hi Eirik , I have found out the estimation setting from board configuration . The second part of my question is how to view resource wise burn down charts e.g. if there are 10 stories , each assigned to a different resource .How can i view resource wise burn down of the same sprint .Look forward to your kind response. Thanks.

I don't think, or even hope, that this is possible. The burndown chart wasn't created to track individual progress, but that of a team.

Also , please suggest that how can we view user wise burn down charts .

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,076 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you