Hi,
We are trying our JIRA Portfolio to see if we can make certain milestones as well as see the impact of new issues being added to our backlog.
However, it seems that there is no automatic way to import issues from the backlog to JIRA Portfolio; you need to manually import them every time which means you will also need to assign initiatives and/or themes every time.
Is there no way to automatically get these issues in your portfolio plan so you can directly see the impact?
Kr,
Reinder
it is possible in JIRA Portfolio 2.0.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.