Xporter - getting each Status by date changed

Timothy Boyer January 8, 2015

I would like to include each status of each item in my project and the date that it changed.

 

Help/Tips appreciated.

5 answers

1 accepted

2 votes
Answer accepted
Fábio Antunes July 10, 2015

Hi @Timothy Boyer,

This feature is now available in Xporter for JIRA R3.4.0. (Xporter Versions)
You could check the documentation here.

Kind Regards,
Fábio Antunes 

2 votes
Rui Rodrigues
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 8, 2015

Hi Timothy,

Can you detail a little more what you want?

Do  you want to get the status and last modified date of all issues from a specific project?

Cheers,

RMRodrigues.

1 vote
Rui Rodrigues
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 12, 2015

Hi,

Currently Xporter for JIRA doesn't allow to do that, but there is an issue related with this feature.

You can follow its status here:http://jira.xpand-it.com/browse/XPORTER-19

Thanks.

RMRodrigues.

0 votes
Timothy Boyer January 12, 2015

I appreciate the feedback, Rui. I am now watching that issue on that project.

0 votes
Timothy Boyer January 8, 2015

Each task in my project is at a particular Status at some point in time. They go from Open to In-Progress to "Review" to Available to Done.

I would like to build an Xporter template which captures the transitions and the dates when they happen.

I have been unable to figure this out from the Templates which come with Xporter. We are running version 3.2.2.

Suggest an answer

Log in or Sign up to answer