Worklog display format

Martin Bayreuther November 13, 2012

Hello all,

I know for sure I read about this issue before but I can't find it any more.

The worklog is displayed in the "friendly" way as "1d 5h 10m".

How can this be configured to display everything in one defined base unit?

Example:

13.17 h (would be the equivalent of the friendly notation above)

Thanks in advance

Martin

1 answer

1 accepted

1 vote
Answer accepted
Zul NS _Atlassian_
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 13, 2012

You can configure this by going to System > Issue Feature > Time Tracking. Change the "Time estimates will be displayed in the following format" to hours. More information, you can visit https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking

Martin Bayreuther November 13, 2012

Yes, this was what I was searching for. Turned out I didn't search properly.

Suggest an answer

Log in or Sign up to answer