Working hours in burndown chart

I would like to have non-working hours excluded from the sprint burndown chart. Is this possible? (I can find configuration for working days only)

1 answer

This page is only about working days, not working hours.

What do you mean by non-working hours?

We work from 9:00 a.m. to 17:00 p.m. but when we have a sprint of one week there are 24 hours in de burndown chart.

Burndown charts shows Issues being closed in a current sprint OR hours being logged to it. If you log 24 hours to an issue, that will be reflected in the burn. OR If a particular Story have 8 points and you close that, it will be reflected too. It depends on what configuration you are using.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,224 views 14 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot