  • Within JIRA, under Boards>configuration>column management, is it possible to change the the colour of new columns,so the furtherst two columns BOTH represent Done? Or is it always the case the furthest left and right represent To Do and Done?

Within JIRA, under Boards>configuration>column management, is it possible to change the the colour of new columns,so the furtherst two columns BOTH represent Done? Or is it always the case the furthest left and right represent To Do and Done?

Henry Kevis June 8, 2016
 

1 answer

1 vote
Steven F Behnke
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 8, 2016

The furthest left is always To Do and the furthest right is always Done.