Why my sprint tasks are marked as done but shows as in progress in the backlog board?

I'm trying to close a sprint but not being able. All my issues are marked done but show as in progress on the backlog.

See images below:

image2016-10-17 11:42:30.png

 

This is my Statuses Configuration

image2016-10-17 11:43:42.png

 

Thanks for your help,

 

Edson

 

1 answer

1 accepted

This widget could not be displayed.

Could you check your board configuration?  Specifically, is the "done" status in the far right hand column of the board?

The column with which Done was associated was not the most far-right column. Changing this fixed it.

 

Many thanks for your help.

That's one I feel the docs and in-application help doesn't really highlight enough!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

124 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you