Why jira portfolio moves one task to next sprint while still capacity available?

Hi,

I have a portfolio plan which seems to keep setting one specific task in a next sprint, while there is still capacity available in the previous sprint. How does this happen?

For information, I'm able to statically assign the item to the current sprint (blue). But when I choose calculate, it creates sprint 3, while in sprint 2 there is still capacity available (red).

 

image2017-1-25 17:5:27.png

image2017-1-25 17:6:26.png

2 answers

This widget could not be displayed.
  1. How many points is DEV-662?
  2. Do you have any filters applied (i know, i know it shouldn't matter but it's becoming a #1 on my checklist of sanity when using Portfolio... it changes things without you realising sometimes).
  3. When you assign it to sprint 11 manually, does it over assign your capacity?
  4. Is there an earliest start date on your dev-662?
This widget could not be displayed.

Hi Aaron,

 

thanks for helping me out here. 

  1. we do estimations in time. It's not estimated yet, so in JPO I have a default of 0.5 days setting, while there is still a few days open capacity, this should (I think) be enough.
  2. No, I disabled filters in the JPO live plan and the boards that are used as source are also unfiltered.
  3. When I add it manually to the active sprint, it works fine. There is no over assign to my capacity.
  4. There is no earliest date set. 

 

Regards,

Jan

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

286 views 1 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you