Why is my epic scheduled to take less time than the estimate (Jira Portfolio)?

I'm attempting to do some high-level planning and estimates with Portfolio. For some reason, it appears to schedule certain Epics as taking less time to complete than the actual estimate itself says. I would expect this Epic to block out 4 days (based on the time estimate it has). This only seems to happen in certain cases.

 

portfolio1.png

Here's the estimate on the ticket (same value is displayed in Portfolio):

 

portfolio2.png

I'm sure the explanation will be logical - I'm just a bit confused at the moment.

2 answers

1 accepted

This widget could not be displayed.

Hi James,

Most likely, you have more than 1 team member scheduled to be working on it. If you have an estimate of 4 days on your epics and 2 people working on it, it will be done in 2 days.

To verify this:

  • look at the Scope view of Portfolio,
  • Make sure you are viewing the epic and have the Team / Members colums visible in the table
  • Have a look how many team members are assigned to work on the epic.

 

Thanks Walter - that turned out to be the case.

I had confused myself with this config option:

Screen Shot 2016-09-28 at 17.35.28.png

I hadn't appreciated that it wasn't also applying to Epics. I'll play with the settings and see what happens.

@James Munro  Did this work for you? 

 

Im running into the same issue. i dont have the stories defined but i have the epics with Estimates at the Epic level but the days blocked arent what i've entered. I've tried to play with the scheduling options without any luck.

I just verfiied that i have no member assigned and it seems like if you dont have anyone assigned it considers that everyone is assigned

This widget could not be displayed.

HI guys, 

 

I'm having the same issue but cant seem to resolve it. My epic has no one assigned to it. It seems like if no one is assigned it assume the whole team is working on it at the same time. Or am i missing something?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

203 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you