Why dose the plan shows no end date in timeline?

tim_leung_kt
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 8, 2024

I create an subtask and try to test timeline plan with custom fields, but it shows No end date in timeline.

Also, is it possible to make the timeline more like a grid style and columned by days?

The timeline display:

1.PNG

The subtask dates' value:
2.PNG

The timeline setting:3.PNG

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 8, 2024

Hi @tim_leung_kt and welcome to the Community!

I would recommend having a good look at your Jira custom fields and make sure there is only one Job End Date field in there. The one that's in your plan has ID 10237; in Jira it's possible to create multiple custom fields with the same name, so if you're looking at the wrong field, it won't display properly.

Hope this helps!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events