Why do "start date" and "due date" get reset automatically?

Art Vega
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 13, 2020

Hi, 

I created a new project in which I forgot to use our customized issue screen, so it took the default screen. The start date was set to 06/17/20, even though I created the task in October 12th 2020. 

I then switched to the customized issue screen in which I have the "due date" as one of the fields. I then tried to update both fields (start date to a particular day last week in the due date a date at the end of this week), but after a few seconds the dates are reverted back to 06/17/20 (even before I refresh the page). 

There are no dependencies on these issues, so I really don't have a clue why this is happening. Any help would be appreciated. If you need any additional info, please let me know. 

Thanks!

/Art

1 answer

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 13, 2020

Hi Art,

I would check to see if there is some type of automation that is setting the dates. You could look at the history of the card to see "who" is changing the value.

But if it is happening real time in the screen then I am suspicious of a default value for the field being set somewhere. But since Due Date and Start Date are "system" fields, that wouldn't be possible. Unless you have created custom fields for those functions. 

Art Vega
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 26, 2020

Hi John, 

Thank you for your time and your suggested solution. I found out the problem was that I had set up a top to bottom alignment of dates for this project in particular.  I fixed that by going back to bottom to top. 

Thanks,

Art

Like John Funk likes this
Andrei Maroz July 29, 2021

Hey @Art Vega I might have similar issue with End Date field. Please could you help me find the place where I can update the allignment of dates for a particular project in Jira.

Jeff Denton September 17, 2024

What was the solution.  I don't understand top to bottom alignment. Please help.

Edoardo Cavallini October 10, 2024

Hi, I have the same issue. Did figure out how to fix this issue? Thanks