Why can I see subtasks in the Kanban Backlog, and not sprint backlog???

I understand subtasks in the backlog is considered "clutter" and generally subtasks dont belong there. 

 

I want to know why , however, in the same Jira project, I have a kanban and sprint board, and I can only see subtasks in the kanban backlog.... but if i go to the sprint backlog, I can only see stories?

 

Is there a fundamental difference between a typical backlog (sprint backlog) and the kanban backlog?

1 answer

1 accepted

1 vote
Answer accepted

Yes, there is a difference, although it's actually the same reason! 

Scrum and Kanban have nothing to say about sub-tasks.  Jira implemented sub-tasks (well before it started to support Scrum and Kanban directly) because a lot of people find them useful in all sorts of processes.  

It is important to understand that Jira's sub-tasks are very much a part of their parent, they're not separate entities or loosely connected, they are a chunk of the overall story.  A good analogy is a jigsaw puzzle.  Your story is "complete a picture", and "put this piece in the right place" is a sub-task of that.  You can't complete the story without every piece being "done", but you can't complete a piece without referring to the story as a whole.

So. 

Scrum backlogs do not show sub-tasks because of exactly what you say - they're noise in the backlog.  The backlog is for ranking, refining, and building a sprint from a list of sprint items.  Sub-tasks are an irrelevance - as part of a bigger story, they can't be ranked outside it, they're not relevant to other stories, and they only go into a sprint as part of their parent item.

Kanban runs every item as a single story.  It does not actually care that an issue is a sub-task, it's just another item that needs doing.  The backlog for Kanban is, again, for ranking and refinement, but it's a simple to-do list.   A sub-task is a Kanban card, so it appears in the backlog with all the other types.

This was so helpful, thank you so much!!!!

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you