Why are my tasks moving back to the backlog after I move them to the current sprint?

Its making me nuts right now

I have tasks that are in the backlog that I move up to a current sprint (starts tomorrow). The Sprint has 13 tasks...when I move these into it, it knocks it up to 18. When I move to the work or report window and then come back.....the sprint is back at 13 and the tasks i just moved are back in the backlog.

The fix versions are right (our current release) and the sprint version is in "fix version" as well as the current sprint. yet it will not stay.

WHY?

1 answer

This widget could not be displayed.

I guess yo have to provide some more information, like what is your board filter setup like? What kind of permissions do you have?

Usual suspects if you begin searching here is that the filter is not ordered by rank and/or people do not have project admin rights on *all* projects the filter touches.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted yesterday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

46 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you