Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,467,803
Community Members
 
Community Events
177
Community Groups

Which is the best way to create similar projects and to manage them in WBS Gantt-Chart?

Hi, I use Jira Cloud and I need to create similar projects (everyone with the same tasks and the same sub-tasks) and to manage them in WBS Gantt-Chart. Any suggestion?

I've tried this way:

  1. I've created a template project with the all the tasks and the sub-tasks that I need
  2. I've cloned the template project with the app "Deep clone for Jira" in order to obtain the same scheme for all the other projects of my company
  3. I've used the app WBS Gantt-Chart to manage the projects created individually and all togheter

Thank you!

1 answer

1 accepted

0 votes
Answer accepted

Hello @Andrea Fontanini , Alessandro from WBS Gantt-Chart support team here. 

Thanks for submitting your question, we are happy to hear that you manage your projects using our App!

In fact, you should be able to perform most of these activities by using the App's Issue Template feature. It allows you to create a set of pre-defined issues and clone them with a single click which, in your case, can be used to create the template project.

The app also allows you to share the template across different Gantt-Charts using the Issue template share project feature. In other words, it allows you to use Issue templates from one Gantt into other Gantts.

Based on your scenario, here's what you can do:

  1. Create a Template Project in Jira and a Gantt chart for it.
    You then add the issues you would like to clone either using Jira or the Gantt-Chart view:
    01.png
  2. After your Template is ready, right-click the parent issue (in this case Ordered Issues) -> Clone into template... -> Add to new template... 
    You can then give a name to it and click "Create" in the prompt that will appear right after selecting the option above:
    02.png

The process above will replicate the issues selected in the Gantt-Chart's "Template" tab:
03.png
Enabling you to add the selected issues whenever you like through the Add button on the Menu bar or the same option when right-clicking inside the Gantt Chart:

04.png

Now, to expand its usage across different Gantt Charts, all you have to do is map this Template Gantt to them using the Issue template share project feature. This will enable you to add the issues from your Template Project to any project you have the feature configured.

Let's say that you just created a new Project and Gantt chart for a new project. It will of course have no issues or templates available on the Add button.
So, in order to add the issues from your Project Template and clone them to this new project - here is what you need to do:

  1. Open the Gantt Chart where you would like to use the template and clone issues. In my case, I created the "Company Managed Project";
  2. From the Gantt-Chart screen, click the Cog Icon of the Gantt-Chart grey toolbar and select Gantt configuration:
    05.png
  3. On the Gantt configuration screen, go to the Issues tab and click on the Edit button at the rightmost corner to customize the settings.
  4. Locate the Issue template share project field and add your Project Template to inherit the issues you want to clone into this new project:
    06.png
    When done, click the Update button to save the changes and then Back to Gantt so you can start using the Template project.
  5. From your Gantt Chart, click the Add button - you will notice that the template will be available as an option. Select it to clone the issues into your new Gantt:
    07.png
  6. The issues will be automatically generated according to the template selected. If everything is according to what was expected, you can click the orange Save button to generate the issues:
    08.png

Hope this helps using the fullest of your WBS Gantt-Chart in your day-to-day activities!
If there is anything else we can help you with, please add a new comment. We will be happy to be of assistance.

Wish you a great day ahead!

Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team

Thank you @Alessandro Portela Cristiano for the answer. I have followed your suggestions, but I still have some problems at step number 4 of your list.

When I open the new project and try to insert the template in Gantt configuration, it doesn't allow me to insert the template project because the name of the template project doesn't appear in the Issue template share project field ("No matches found").

In the screenshot below "PXX23-CLIENTE TEMPLATE" is the name of the project template (and not the name of the WBS Gantt Chart), but it doesn't appear in the field.

This way I can't add the template and I can't go on. Any suggestion?

Thank you

Jira2.jpg

You are welcome @Andrea Fontanini!

It may be possible that PXX23 is not being displayed on the list because of its Project Type (it is a Business Project from what I could Google Translate, correct?).

WBS Gantt-Chart features are mostly compatible with Company-Managed Projects.
Unfortunately, the very nature of Business or Team-managed projects prevents some features of the app from being implemented at the moment.

In this case, I would recommend Migrate between team-managed and company-managed projects and then trying again.

Please note that the project migration may be necessary not only for the Template Project but for your other projects as well and, since you are modifying data in bulk, a backup is always recommended to prevent data loss.

Please, do keep the questions coming!

Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team

Like Andrea Fontanini likes this

Thank you @Alessandro Portela Cristiano . I've created a new Company-Managed Project and now it's possible to use issues frome shared templates coming from other Company-Managed Projects.

Happy to hear that, @Andrea Fontanini !

Let us know if we can help you with anything else. It will be our pleasure to be of assistance.

Wish you all the best.

Kind Regards,

Alessandro C. | Support Engineer
Ricksoft Support Team

Like Andrea Fontanini likes this

Hi @Andrea Fontanini 

Thank you very much for sharing the other posts with us!

The responses are already on their way!
If possible, please keep tagging our app in the 'Tags' section of your post - it will make it easier to find WBS Gantt-Chart specific topics between everything that happens in this huge community. :)

In any case, we appreciate your constant feedback and questions. Please feel welcome to reach us whenever needed!

All the best,
Alessandro C.
Ricksoft Support Team