Which Sprint report or velocity chart should be trusted for actual committed vs completed

Gautam Salwan February 11, 2019

The Story Points for on my Sprint report show 108 points ( this includes the total of Completed,Not Completed and Removed issues) for the particular sprint

However the Velocity chart report shows a total commitment of 137 story points

This discrepancy is causing mistrust in the data by my teams and would like to learn

1. Is there a way to fix both to show correctly the same correct data

2. If point one is not possible then guide which as per Jira is dependable of the two Sprint report or Velocity chart for seeing total committed  and total completed story points.

3. Lastly where did the additional story points come from in the Velocity chart

 

I went through the community page but it pointed that there is a bug in Jira ( however thats old info , i am assuming Jira would have fixed it by now)

 

Thanks 

 

Gautam

About my Jira below:

 

Jira credits

Roll credits...

License Information for Jira

Jira 27231577

Copyright © 2002 - 2019 Atlassian Corporation Pty Ltd.

The use of this product is subject to the terms of the Atlassian End User Agreement, unless other specified therein.

This product includes software developed by the Apache Software Foundation.

This product also includes code written by other third parties.

License Information for Jira Plugins

 

Jira Service Desk Application 3.3.0-OD

 

Copyright © 2002 - 2018 Atlassian Corporation Pty Ltd.

 

1 answer

0 votes
Zach Grove October 9, 2019

Any solution to this @Gautam Salwan?

Gautam Salwan October 10, 2019

Zach since I did not get a response from Jira I ;ve been tracking them manually and trust my data as it could be explained. If you find out please post on the community and we can learn how to tackle this- Thx