  • When completing a sprint, stats display for "Done", "Incomplete" and "Partially Complete" statuses. What is the difference between "Incomplete" and "Partially Complete"?

When completing a sprint, stats display for "Done", "Incomplete" and "Partially Complete" statuses. What is the difference between "Incomplete" and "Partially Complete"?

Olive June 8, 2016
 

2 answers

1 accepted

0 votes
Answer accepted
Petar Petrov (Appfire)
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 8, 2016
  • Partially complete issues are issues which have subtasks, where some of the subtasks were completed during the sprint.
  • Incomplete issues are the issues that are not done, minus any partially completed issues.
0 votes
Olive June 8, 2016

Thank you!! Makes perfect sense!