  • When completing a sprint, stats display for "Done", "Incomplete" and "Partially Complete" statuses. What is the difference between "Incomplete" and "Partially Complete"?

When completing a sprint, stats display for "Done", "Incomplete" and "Partially Complete" statuses. What is the difference between "Incomplete" and "Partially Complete"?

 

2 answers

1 accepted

0 votes
Accepted answer
  • Partially complete issues are issues which have subtasks, where some of the subtasks were completed during the sprint.
  • Incomplete issues are the issues that are not done, minus any partially completed issues.

Thank you!! Makes perfect sense!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,772 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you