When a story is closed can all subtasks also be closed at this time (with a warning)

AW February 11, 2015

how would such magic be performed?

1 answer

1 vote
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 13, 2015

If you use JIRA Agile, there is an option to it. Without that, you will need some customizations on your end.

AW February 26, 2015

I do use jira agile but cannot find the switch! can you point me to it?

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2015

it is not a switch. Configure the board to use swimlanes based on Stories. You will then get an option to close the parent story when the last subtask is resolved. Note that you won't be able to move stories with subtasks, from one column to another, in this setup. Stories without subtasks can still be moved.