What is the best way to modify planned time?

I am planning developers activities with Tempo, which requires me to plan items like:

PRJ-8 4 hours a day from 15/11 to 30/11.

That's fine, but often I need to revise planning because an activity has been delayed, and, for instance, I would like to modify the previous entry into

PRJ-8 4 hours a day from 20/11 to 07/12.

Currently the only way I found is to delete the old planning and re-enter it. Is there a better way? e.g. to "move" or "edit" the existing planning?

Thanks

1 answer

1 accepted

0 votes
Accepted answer

Hi

You can edit the description and date for a plan. You can not edit date range so in your case you need to delete the plan and add a new one.

We are aware of this behavior and are working on some improvements.

Best regards

Sverrir Tynes
Tempo support

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,310 views 12 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you