What are the impact on Sprints and Filters if the associated Project is deleted in JIRA?

sandeep sankalapur July 2, 2014

The above information is required, since while migrating the project from one Jira instance to another, we first deleting the project in Instance A & then importing the Project from Instance B to Instance A.

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 2, 2014

The filters will be broken. You will have to remove the project from the filter manually. Sprints are not directly linked to projects but the board filter will also be broken.